Space Systems Engineering Self-Study Sequence

A phased path through the [[Space Systems Engineering Curriculum]]. It assumes an engineering degree or equivalent: comfort with calculus, basic dynamics and some scripting.

Running design project

Each phase produces one artefact for a single reference mission that you carry through to a self-run PDR. The capstone then becomes the accumulation of real work rather than a separate exercise. Pick something scoped enough to finish, for example:

Keep everything in a project folder (e.g. Projects/SSE Reference Mission/) and link each artefact back to the phase that produced it.

Abbreviations: NASA SEH = NASA Systems Engineering Handbook; SME = Space Mission Engineering: The New SMAD; FSS = Fortescue, Swinerd & Stark.


Phase 0 — Orientation (weeks 1–2)

Goal: a mental model of the whole life cycle before going deep on anything.

Artefact: a one-page mission statement for the reference mission (objective, user, rough timeline).


Phase 1 — Front-end SE: needs, ConOps, requirements (weeks 3–7)

Goal: turn a mission idea into a verifiable requirements set.

Artefacts:

Checkpoint — self-run MCR/SRR

Can every requirement be traced to a need? Is each one verifiable and free of design solutions?


Phase 2 — Space environment and astrodynamics (weeks 8–13)

Goal: enough orbital mechanics and environment knowledge to choose and justify an orbit.

Artefacts:


Phase 3 — Architecture and system budgets (weeks 14–18)

Goal: a functional and physical architecture with closed budgets.

Artefacts:


Phase 4 — Subsystems (weeks 19–28)

Goal: first-order sizing of every subsystem, with interactions closed against the Phase 3 budgets. Allow about one week per subsystem block.

WeekSubsystemReadingSizing output
19[[Propulsion]]FSS propulsion; Sutton & Biblarz (selected chapters)Propellant mass, thruster selection
20–21[[ADCS and GNC]]FSS attitude control; SME ADCS chapterDisturbance torques, actuator sizing, pointing budget
22[[Electrical Power System]]FSS power; SME power chapterArray area (EOL), battery capacity (DoD)
23[[Thermal Control]]Gilmore (selected); FSS thermalHot/cold case single-node model, radiator area
24[[Structures and Mechanisms]]FSS structures; launch vehicle user's guidePrimary structure concept, frequency requirement
25[[Communications and TT&C]]FSS telecommunications; SME comms chapterLink budget closed with margin
26[[Command and Data Handling]] + [[Flight Software]]FSS OBDH; Pisacane C&DHData budget, mode diagram, FDIR concept
27[[Payloads]]Mission-specific literaturePayload requirements allocation
28Integration week—Re-close all budgets, update ICDs

Budgets will break

Expect week 28 to reopen earlier decisions. Iterating is the systems engineering work, not a failure of it. Record each change in the decision log.


Phase 5 — Verification, reliability and operations (weeks 29–32)

Artefacts:


Phase 6 — Capstone: self-run PDR (weeks 33–36)

Artefacts:


Progress log

PhaseStartedCompletedNotes
0 Orientation
1 Front-end SE
2 Environment & astrodynamics
3 Architecture & budgets
4 Subsystems
5 V&V, reliability, ops
6 Capstone PDR