<p>Retention&#160;is a percentage (often 5%) of the amount certified as due to the&#160;contractor&#160;on an&#160;interim certificate, that is deducted from the amount due and retained by the&#160;client. The purpose of&#160;retention&#160;is to ensure that the&#160;contractor&#160;properly completes the activities required of them under the contract.&#160;Retention&#160;can also be applied to&#160;nominated sub-contractors, and the&#160;main contractor&#160;may also apply&#160;retention&#160;to&#160;domestic sub-contractors.