WATERBURY LAKE PROPERTY

Waterbury

As we continue to advance this exciting project we will post the latest maps and photos. Click icons to view.

DETAILED

MAPS](https://www.denisonmines.com/projects/core-projects/waterbury-project/#modal-maps)

RECENT

PHOTOS](https://www.denisonmines.com/projects/core-projects/waterbury-project/#modal-images)

DRONE

VIDEO](https://www.denisonmines.com/projects/core-projects/waterbury-project/#modal-video)

FEATURED

VIDEO](https://www.denisonmines.com/projects/core-projects/waterbury-project/#modal-video-2)

Host to the Tthe Heldeth Túé (formerly J Zone) and Huskie uranium deposits.

Denison has completed an independent Preliminary Economic Assessment (“PEA”) for the Waterbury Lake Property evaluating the potential use of the In-Situ Recovery “ISR” mining method at the Tthe Heldeth Túé (“THT”) deposit with processing at Denison’s 22.5% owned McClean Lake mill.

The PEA demonstrates robust economics for a small-scale Athabasca Basin ISR uranium mining project – including low initial capital costs, low operating costs and globally competitive all-in costs. (See press release Nov 2020).

Preliminary Economic Assessment Highlights (see below for details):

The information on this page is from the November 17, 2020 news release reporting the results from the 2020 Waterbury Preliminary Economic Assessment filed on December 30, 2020.

The PEA is available in link: Waterbury PEA December 2020

Tthe Heldeth Túé

The Ya’thi Néné Land and Resource Office working together with Denison, reviewed the Conceptual Mining Study prepared by Denison for the J Zone deposit prior to initiation of the PEA (see news release dated July 28, 2020). The YNLR provided valuable early feedback related to the Project’s next steps, and recommended the use of a Dené name for the deposit that would recognize and respect the connection of the Athabasca Denesųłiné to the land where the deposit is located: the “Tthe Heldeth Túé” deposit – pronounced “Tey Hel-deth Tway”.

Location

The Waterbury Lake property is located within the eastern part of the Athabasca Basin in Northern Saskatchewan. The property can be accessed year-round by provincial highway to Points North Landing, a privately owned service centre with accommodations and an airfield, which is located near the eastern edge of the property. Several uranium mills and mines are located close to the deposit.

Ownership

Waterbury is owned by the Waterbury Lake Uranium Limited Partnership (“WLULP”), of which Denison Waterbury Corp. (a wholly-owned subsidiary of Denison) owns 66.90% and Korea Waterbury Lake Uranium Limited Partnership (“KWULP”) owns 33.10% (as of end of November 2020). KWULP is comprised of a consortium of investors, in which Korea Hydro & Nuclear Power (“KHNP”) holds a majority position. KHNP is headquartered in Gyeongju, South Korea and is the country’s largest electrical power generation company, operating 24 nuclear power reactors and supplying approximately one-quarter of the country’s electricity. KHNP is also a significant shareholder in Denison.

Preliminary Economic Analysis

Waterbury PEA Financial Results (100% Basis)

The technical report, prepared in accordance with 43-101,vwas completed in 2020. The highlights of the PEA are:

Mine life~ 6 years (Avg. ~1.6 million lbs U3O8per year)
Projected mine production (1)9.7 million lbs U3O8(177,664 tonnes at 2.49%)
Average cash operating costsUSD$12.23 ($16.27) per lb U3O8
Initial capital costs (2)$112 million
Base case pre-tax IRR (3)39.1%
Base case pre-tax NPV8% (3)$177 million
Base case price assumptionUxC spot price(4)(Avg. USD$53.59 per lb U3O8)
Operating profit margin (5)77% at USD$53.59 per lb U3O8
All-in cost (6)USD$24.93 ($33.16) per lb U3O8
  1. Projected mine production uses an 85% ISR recovery factor and excludes sterilized and unavailable areas of the THT deposit.
  2. Initial capital costs exclude $20.1 million of estimated pre-construction Project evaluation and development costs.
  3. NPV and IRR are calculated to the start of pre-production activities for the THT operation in 2025.
  4. Spot price forecast is based on “Composite Midpoint” scenario from UxC’s Q3’2020 Uranium Market Outlook (“UMO”) for the years 2028 to 2033, and is stated in constant (not-inflated) dollars.
  5. Operating profit margin is calculated as uranium revenue less operating costs, divided by uranium revenue. Operating costs exclude all royalties, surcharges and income taxes.
  6. All-in cost is estimated on a pre-tax basis and includes all project operating costs and capital costs, excluding project evaluation and development costs, divided by the estimated number of pounds U3O8to be produced at the mill.

The PEA is preliminary in nature shall not be considered as a Pre-Feasibility or Feasibility Study. It includes indicated mineral resources and ISR mining recovery factor that are considered too speculative geologically to have the economic considerations applied to them to be categorized as mineral reserves, and there is no certainty that the preliminary economic assessment will be realized. Mineral resources are not mineral reserves and do not have demonstrated economic viability.

Preliminary Economic Assessment Highlights:

Price Assumptions & Sensitivities

The base-case economic analysis assumes uranium sales will be made from time to time throughout production at UxC’s forecasted annual “Composite Midpoint” spot price from the Q3’2020 Uranium Market Outlook (“UMO”), which is stated annually in constant (non-inflated) 2020 dollars and ranges from ~USD$49 per lb U3O8 to USD$57 per lb U3O8 during the approximate six year estimated life of the THT operation (assumed for pricing purposes to be from 2028 to 2033). The average base case selling price is USD$53.59 per lb U3O8.

Given the estimated all-in costs of USD$24.93 per lb U3O8, the Project is projected to be able to generate positive economic results at uranium selling prices in the range of recent market conditions, while also offering excellent leverage to a rising uranium price, as outlined below:

Table 4 – Sensitivity of Waterbury to Uranium Pricing Scenarios (100% Basis)Table 4 – Sensitivity of Waterbury to Uranium Pricing Scenarios (100% Basis)Table 4 – Sensitivity of Waterbury to Uranium Pricing Scenarios (100% Basis)Table 4 – Sensitivity of Waterbury to Uranium Pricing Scenarios (100% Basis)
Low CaseBase caseHigh Case
Uranium priceUSD$35 per lb U3O8UxC spot price (3)USD$65 per lb U3O8
Pre-tax NPV8% (1)$38 million$ 177 million$ 265 million
Pre-tax IRR (1)17.4%39.1%50.0%
Pre-tax payback period (2)33 months22 months18 months
  1. NPV and IRR are calculated to the start of pre-production activities for the Project.
  2. Payback period is stated as number of months to pay-back from the start of uranium production.
  3. Spot price forecast is based on “Composite Midpoint” scenario from UxC’s Q3’2020 Uranium Market Outlook (“UMO”) for the years 2028 to 2033 and is stated in constant (not-inflated) dollars.

Indicative Denison Post-Tax Results

The PEA is prepared on a pre-tax and 100% ownership basis, as each partner to the WLULP is subject to different tax and other obligations. Denison has completed an indicative post-tax assessment that reflects its ownership interest in the WLULP (66.90%), the impact of expected toll mill fees recovered from its 22.5% interest in the MLJV, and the benefit of Denison’s applicable existing tax shelter balances.

Net Saskatchewan sales royalties consist of the resource surcharge (3%), and the basic uranium royalty (5%), which is partially offset by the resource credit (0.75%). These amounts are included in the pre-tax NPV calculations throughout the PEA; however, they are excluded from the U3O8 operating cost per pound metrics, as they vary with the value of assumed uranium sales. The profit from operations is subject to an additional Provincial uranium profit royalty, which is treated as an income tax, and allows for the use of certain tax shelter balances.

Denison’s post-tax indicative results for the THT project are summarized below and are based on the prevailing Federal and Provincial taxation regulations in place at the time of the PEA as well as Denison’s 66.90% ownership of the property as of the end of November 2020.

Table 9 – Denison Indicative Post-Tax Results (66.90% ownership)Table 9 – Denison Indicative Post-Tax Results (66.90% ownership)
Initial capital costs – Denison Share (1)$75 million
Base case post-tax IRR (2)30.4%
Base case post-tax NPV8% (2)$72 million
Base case post-tax payback period (3)~ 23 months
High case post-tax IRR (2)38.9%
High case post-tax NPV8% (2)$109 million
High case post-tax payback period (3)19 months
Low case post-tax IRR (2)13.5%
Low case post-tax NPV8% (2)$14 million
Low case post-tax payback period (1)34 months
  1. Initial capital cost excludes estimated pre-construction Project evaluation and development costs
  2. NPV and IRR are calculated to the start of pre-production activities for the THT operation.
  3. Payback period is stated as number of months to pay-back from the start of uranium production.

The PEA is preliminary in nature and should not be considered the same as a Pre-Feasibility or Feasibility Study, as various factors are considered too speculative to have the economic considerations applied to them to be categorized as mineral reserves. There is no certainty that the results from the PEA will be realized. Mineral resources are not mineral reserves and do not have demonstrated economic viability.

For further information please see press release and PEA

Estimated Mineral Resources

DepositClassificationTonnesGrade % U3O81000 Lbs U3O8
Tthe Heldeth TúéIndicated291,0002.0012,810
HuskieInferred268,0000.965,687

Notes:

  1. Mineral resources are not mineral reserves and have not demonstrated economic viability. All figures have been rounded to reflect the relative accuracy of the estimates.
  2. The Tthe Heldeth Túé Mineral Resource estimate was prepared for the Company by GeoVector Management Inc. in accordance with CIM Definition Standards (2005) and NI 43-101 with an effective date of September 6, 2013.
  3. The audited Mineral Resource Statement for the Huskie deposit was prepared by Dr. Oy Leuangthong, PEng and Mr. Cliff Revering of SRK Consulting (Canada) Inc. with an effective date of October 17, 2018.
  4. Mineral resources for the THT deposit are reported above a cut-off grade of 0.1% U3O8.
  5. Mineral resources for the Huskie deposit are reported above a cut-off grade of 0.1% U3O8.

References

“Technical Report with an Updated Mineral Resource Estimate for the Waterbury Lake Property, Northern Saskatchewan, Canada”, dated December 21, 2018.

The technical information has been reviewed and approved by Mr. David Bronkhorst, P.Eng, Denison's Vice President, Operations, who is a Qualified Person in accordance with the requirements of NI 43-101.

The Mineral Resource Estimates have been reviewed and approved by Mr. Andy Yackulic, Denison's Director, Exploration, who is a Qualified Person in accordance with the requirements of NI 43-101.


Table 14-12: Audited Mineral Resource Statement*, Huskie Deposit, Waterbury Lake Uranium Project, Saskatchewan, SRK Consulting (Canada) Inc., October 17, 2018.

Category

Inferred Total Inferred

INFERRED Zone Tonnage Grade CONTAINED METAL

                     (KT)   (%U3)8)  (x1,000 lbs U3O8)

Huskie 1 81 0.34 612

Huskie 2 178 1.28 5,047

Huskie 3 8 0.15 27

TOTAL INFERRED 268 0.96 5,687