NIST SP 800-53r5 — SI-13(03) Manual Transfer Between Components
source: false
type: canonical-control-reference
standard: NIST SP 800-53r5
assessment_standard: NIST SP 800-53Ar5
baseline_standard: NIST SP 800-53B
control_id: "SI-13(03)"
family_id: "SI"
family: "System and Information Integrity"
title: "Manual Transfer Between Components"
status: active
updated: 2026-09-10
authoritative_sources:
- "NIST SP 800-53r5 verified transcription"
- "NIST SP 800-53Ar5 verified transcription"
- "NIST SP 800-53B verified transcription"
baseline_membership:
low: false
moderate: false
high: false
privacy: false
SI-13(03) Manual Transfer Between Components
Canonical combined reference
Control text and discussion come from NIST SP 800-53r5; assessment procedures come from NIST SP 800-53Ar5; baseline membership comes from NIST SP 800-53B.
NIST SP 800-53r5 — Control
Manually initiate transfers between active and standby system components when the use of the active component reaches [Assignment: organization-defined percentage] of the mean time to failure.
Discussion
For example, if the MTTF for a system component is 100 days and the MTTF percentage defined by the organization is 90 percent, the manual transfer would occur after 90 days.
Related Controls
- None specified.
Supporting Publications
- None specified.
NIST SP 800-53Ar5 — Assessment Procedure
Assessment Objective
Determine if:
-
SI-13(03)_ODP— the percentage of the mean time to failure for transfers to be manually initiated is defined; -
SI-13(03)— transfers are initiated manually between active and standby system components when the use of the active component reaches <SI-13(03)_ODPpercentage> of the mean time to failure.
Potential Assessment Methods and Objects
Examine
Select from:
- System and information integrity policy.
- system and information integrity procedures.
- procedures addressing predictable failure prevention.
- system design documentation.
- system configuration settings and associated documentation.
- system audit records.
- system security plan.
- other relevant documents or records.
Interview
Select from:
- Organizational personnel responsible for MTTF activities.
- organizational personnel with information security responsibilities.
- system/ network administrators.
- organizational personnel with contingency planning responsibilities.
Test
Select from:
- Organizational processes for managing MTTF and conducting the manual transfer between active and standby components.
References
Source Assessment Procedure — NIST SP 800-53Ar5
- NIST SP 800-53Ar5 SI-13(03)
NIST SP 800-53B — Baseline Membership
| Baseline | Membership |
|---|---|
| Low | Not included |
| Moderate | Not included |
| High | Not included |