Secure Controls Framework 2026.2 — BCD-06 Ongoing Contingency Planning
source: false
type: canonical-control-reference
standard: Secure Controls Framework 2026.2
control_id: "BCD-06"
domain_id: "BCD"
domain: "Business Continuity & Disaster Recovery"
title: "Ongoing Contingency Planning"
status: active
validation_cadence: "Annual"
relative_control_weighting: "8"
pptdf_applicability: "Process"
nist_csf_function: "Recover"
updated: 2026-09-10
authoritative_sources:
- "SCF 2026.2 workbook"
- "SCF Overview & Practitioner Guidebook, version 2026.2"
source_sheet: "SCF 2026.2"
source_row: 289
source_workbook_sha256: "9e0a4df4993726c95e636f04b3028d8b5edeba2bda45d16ed6722b13540e6835"
source_fidelity_audit: "2026-09-13"
BCD-06 Ongoing Contingency Planning
Canonical SCF 2026.2 reference
Control content, assessment objectives, evidence requests, compensating controls, and mappings come from the official SCF 2026.2 workbook.
Source and mapping limits
This card preserves the retained SCF 2026.2 workbook. Framework mappings are SCF cross-references, not proof of equivalence or compliance. Suggested solutions, maturity descriptions, and possible compensating controls require applicability review; they are not additional mandatory control requirements.
SCF 2026.2 — Control
Mechanisms exist to update contingency plans due to changes affecting:
-
(1)People (e.g., personnel changes); -
(2)Processes (e.g., new, altered or decommissioned business practices, including third-party services) -
(3)Technologies (e.g., new, altered or decommissioned technologies); -
(4)Data (e.g., changes to data flows and/or data repositories); -
(5)Facilities (e.g., new, altered or decommissioned physical infrastructure); and/or -
(6)Feedback from contingency plan testing activities.
Domain Principle
Business Continuity & Disaster Recovery (BCD): Maintain resilient capabilities to sustain business-critical functions and recover from disruptions through documented, tested and maintained continuity and recovery processes.
Organizations establish, exercise and improve Business Continuity and Disaster Recovery (BC/DR) capabilities to minimize operational disruption from adverse events, meet recovery objectives and support business, legal, regulatory and stakeholder obligations.
Control Question
Does the organization update contingency plans due to changes affecting:
-
(1)People (e.g., personnel changes); -
(2)Processes (e.g., new, altered or decommissioned business practices, including third-party services) -
(3)Technologies (e.g., new, altered or decommissioned technologies); -
(4)Data (e.g., changes to data flows and/or data repositories); -
(5)Facilities (e.g., new, altered or decommissioned physical infrastructure); and/or -
(6)Feedback from contingency plan testing activities?
Operational Metadata
| Field | Value |
|---|---|
| Conformity validation cadence | Annual |
| Relative control weighting | 8 |
| PPTDF applicability | Process |
| NIST CSF function grouping | Recover |
Possible Solutions & Considerations
Micro-Small Business
- Documentation change control
Small Business
- Documentation change control
Medium Business
- Documentation change control
Large Business
- Documentation change control
Enterprise
- Documentation change control
Assessment Objectives
BCD-06_A01
a contingency plan is developed that identifies essential mission and business functions and associated contingency requirements.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02a.01
Assessment rigor:
- 1
NIST SP 800-53A:
-
x
BCD-06_A02
personnel or roles to review a contingency plan is/are defined.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02_ODP[01]
Assessment rigor:
- 1
NIST SP 800-53A:
-
x
BCD-06_A03
the contingency plan is updated to address changes to the organization, system or environment of operation.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02e.[01]
Assessment rigor:
- 1
NIST SP 800-53A:
-
x
BCD-06_A04
contingency plan changes are communicated to key contingency personnel.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02f.[01]
Assessment rigor:
- 1
NIST SP 800-53A:
-
x
BCD-06_A05
the contingency plan is updated to address problems encountered during contingency plan implementation, execution or testing.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02e.[02]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A06
personnel or roles to approve a contingency plan is/are defined.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02_ODP[02]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A07
key contingency personnel (identified by name and/or by role) to whom copies of the contingency plan are distributed are defined.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02_ODP[03]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A08
key contingency organizational elements to which copies of the contingency plan are distributed are defined.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02_ODP[04]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A09
the frequency of contingency plan review is defined.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02_ODP[05]
Assessment rigor:
- 3
SCF-defined parameters:
-
at least annually
NIST SP 800-53A:
-
x
BCD-06_A10
key contingency personnel (identified by name and/or by role) to communicate changes to are defined.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02_ODP[06]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A11
key contingency organizational elements to communicate changes to are defined.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02_ODP[07]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A12
a contingency plan for the system is developed that provides recovery objectives.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02a.02[01]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A13
a contingency plan for the system is developed that provides restoration priorities.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02a.02[02]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A14
a contingency plan for the system is developed that provides metrics.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02a.02[03]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A15
a contingency plan for the system is developed that addresses contingency roles.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02a.03[01]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A16
a contingency plan for the system is developed that addresses contingency responsibilities.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02a.03[02]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A17
a contingency plan for the system is developed that addresses assigned individuals with contact information.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02a.03[03]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A18
a contingency plan for the system is developed that addresses maintaining essential mission and business functions despite a disruption, compromise or failure of a system, application or service.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02a.04
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A19
a contingency plan for the system is developed that addresses eventual, full-system restoration without deterioration of the controls originally planned and implemented.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02a.05
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A20
a contingency plan for the system is developed that addresses the sharing of contingency information.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02a.06
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A21
a contingency plan for the system is developed that is reviewed by personnel or roles.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02a.07[01]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A22
a contingency plan for the system is developed that is approved by personnel or roles.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02a.07[02]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A23
copies of the contingency plan are distributed to key contingency personnel.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02b.[01]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A24
copies of the contingency plan are distributed to organizational elements.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02b.[02]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A25
contingency planning activities are coordinated with incident handling activities.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02c.
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A26
the contingency plan for the system is reviewed frequently.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02d.
Assessment rigor:
- 3
SCF-defined parameters:
-
at least annually
NIST SP 800-53A:
-
x
BCD-06_A27
contingency plan changes are communicated to organizational elements.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02f.[02]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A28
lessons learned from contingency plan testing or actual contingency activities are incorporated into contingency testing.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02g.[01]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A29
lessons learned from contingency plan training or actual contingency activities are incorporated into contingency testing and training.
PPTDF applicability:
- Process
Origin(s):
-
53A_R5_CP-02g.[02]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A30
the contingency plan is protected from unauthorized disclosure.
PPTDF applicability:
- Technology
Origin(s):
-
53A_R5_CP-02h.[01]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
BCD-06_A31
the contingency plan is protected from unauthorized modification.
PPTDF applicability:
- Technology
Origin(s):
-
53A_R5_CP-02h.[02]
Assessment rigor:
- 3
NIST SP 800-53A:
-
x
Evidence Requests
-
E-BCM-05— COOP Updates (Business Continuity): Documented evidence of a periodic review process for the organization's Continuity of Operations Plan (COOP) to identify necessary updates.
Compensating Controls
Risk if Primary Control Is Not Implemented
Without Ongoing Contingency Planning, residual security, compliance, or resilience risk may accumulate, potentially leading to control failures or non-compliance.
Possible Compensating Control 1
RSK-07 — Risk Assessment Update
Mechanisms exist to routinely update risk assessments and react accordingly upon identifying new security vulnerabilities, including using outside sources for security vulnerability information.
Justification:
Risk Assessment Update (RSK-07) provides periodic assessment and assurance that compensates for the absence of Ongoing Contingency Planning (BCD-06) by providing structured evaluation of the environment to surface gaps and verify residual control effectiveness. Given the process-oriented nature of this control, this compensating control targets the same underlying risk objective through an alternative approach, helping to maintain an acceptable level of residual risk until the primary control can be implemented.
Possible Compensating Control 2
BCD-01 — Business Continuity Management System (BCMS)
Mechanisms exist to facilitate the implementation of contingency planning controls to help ensure resilient Technology Assets, Applications and/or Services (TAAS) (e.g., Continuity of Operations Plan (COOP) or Business Continuity & Disaster Recovery (BC/DR) playbooks).
Justification:
Business Continuity Management System (BCMS) (BCD-01) provides resilience and recovery capability that compensates for the absence of Ongoing Contingency Planning (BCD-06) by ensuring the organization can restore operations and data when the primary control is absent. Given the process-oriented nature of this control, this compensating control targets the same underlying risk objective through an alternative approach, helping to maintain an acceptable level of residual risk until the primary control can be implemented.
Applicability and Profile Membership
- SCRM Focus TIER 2 OPERATIONAL: Included
- SCRM Focus TIER 3 TACTICAL: Included
- SCR-CMM Level 0 Not Performed:
Practices are non-existent, based on the inability to demonstrate an implemented and operational capability. A reasonable person would conclude the control is not being performed.
- SCR-CMM Level 1 Performed Informally:
SCR-CMM Level 1 criteria definitions are not available for this control:
- A reasonable person would conclude this control requires a structured process.
- At this level of maturity, the "ad hoc" nature of performing a capability informally would indicate the intent of the control is not met due to a lack of consistency and formality.
- SCR-CMM Level 2 Planned & Tracked:
Business Continuity & Disaster Recovery (BCD) capabilities are requirements-driven, but are not standardized across the entity (e.g., local/regional level consistency). Capability criteria associated with this control reasonably expect the following criteria to exist:
- Policies and standards associated with BCD domain capabilities are formally documented and centrally-managed by the entity.
- Standardized Operating Procedures (SOP) associated with BCD domain capabilities are documented and maintained by process owners.
- IT and/or cybersecurity personnel work with business stakeholders and process owners to appropriately scope and reasonably implement cybersecurity and data protection controls associated with BCD domain capabilities to address applicable statutory, regulatory and/or contractual requirements for Technology Assets, Applications, Services and/or Data (TAASD).
- Business Continuity / Disaster Recovery (BC/DR)-related controls are primarily administrative and preventative in nature (e.g., policies, standards, procedures & guidelines).
- BC/DR may be a defined function (e.g., team or department) or assigned as an additional duty to existing IT and/or cybersecurity personnel.
- Production TAASD support business-critical application and services failover.
- IT and/or cybersecurity personnel work with business stakeholders and process owners to develop BC/DR plans to recover business-critical TAASD.
- Data/process owners conduct a Business Impact Analysis (BIA) at least annually, or after any major technology or process change, to identify TAASD that are critical to the business, as well as single points of failure.
- Business stakeholders and process owners designate alternative decision-makers if primary decision-makers are unavailable.
- Within the BC/DR plans, alternate communications channels are defined if primary means of communication are unavailable.
- RTOs are used to identify business-critical TAASD, which are given priority of service in alternate processing and storage sites.
- SCR-CMM Level 3 Well Defined:
Business Continuity & Disaster Recovery (BCD) capabilities are standardized across the entity for applicability to People, Processes, Technologies, Data and/or Facilities (PPTDF) to ensure consistency for Technology Assets, Applications, Services and/or Data (TAASD). Capability criteria associated with this control reasonably expect the following criteria to exist:
- Policies and standards associated with BCD domain capabilities are formally documented and centrally-managed by the entity's Governance, Risk & Compliance (GRC) team, or similar function.
- Standardized Operating Procedures (SOP) associated with BCD domain capabilities are well-documented and kept current by process owners.
- A Business Continuity & Disaster Recovery (BC/DR) team, or similar function, is appropriately staffed and supported to implement and maintain BCD domain capabilities.
- Technology is leveraged to enhance the efficiency and accuracy of BC/DR operations (e.g., BC/DR planning software, Disaster Recovery as a Service (DRaaS), Orchestration and Automation Tools, etc.).
- The entity's Governance, Risk & Compliance (GRC) team, or similar function, works with business stakeholders and process owners to appropriately scope and reasonably implement cybersecurity and data protection controls associated with BCD domain capabilities to address Minimum Compliance Requirements (MCR) (e.g., applicable statutory, regulatory and/or contractual requirements) and Discretionary Security Requirements (DSR) (e.g., entity-required controls).
- An implemented and operational capability exists to update contingency plans due to changes affecting:
- (1) People (e.g., personnel changes);
- (2) Processes (e.g., new, altered or decommissioned business practices, including third-party services)
- (3) Technologies (e.g., new, altered or decommissioned technologies);
- (4) Data (e.g., changes to data flows and/or data repositories);
- (5) Facilities (e.g., new, altered or decommissioned physical infrastructure); and/or
- (6) Feedback from contingency plan testing activities.
- SCR-CMM Level 4 Quantitatively Controlled:
Business Continuity & Disaster Recovery (BCD) capabilities, in addition to being standardized across the entity and centrally managed to ensure consistency across Technology Assets, Applications, Services and/or Data (TAASD), efforts are metrics driven to provide sufficient insight for decision makers to predict optimal performance, ensure continued operations and/or identify areas for improvement. Capability criteria associated with this control reasonably expect the following criteria to exist:
- Applicable SCR-CMM Level 3 (Well Defined) capabilities are implemented and operational.
- Metrics reporting includes quantitative analysis of Key Performance Indicators (KPIs).
- Metrics reporting includes quantitative analysis of Key Risk Indicators (KRIs).
- Scope of metrics, KPIs and KRIs covers organization-wide cybersecurity and data protection controls, including functions performed by third-parties.
- Organizational leadership maintains a formal process to objectively review and respond to metrics, KPIs and KRIs (e.g., monthly or quarterly review).
- Based on metrics analysis, process improvement recommendations are submitted for review and are handled in accordance with change control processes.
- Business and technical stakeholders are involved in reviewing and approving proposed changes to evolve capabilities.
- SCR-CMM Level 5 Continuously Improving:
Utilize SCR-CMM Level 3 or Level 4 (if available) criteria definitions:
- There are no defined Level 5 criteria, since it is reasonable to assume a continuously-improving process is not necessary to operationalize this control.
- Level 5 capabilities should be considered “world-class” where the control builds on Level 4 capabilities, but are continuously improving through Artificial Intelligence (AI) and/or Machine Learning (ML) technologies.
- While it may be possible to develop responsive capabilities for this control through the use of AI and/or ML technologies, the criteria would be organization-specific to define.
- SCF CORE ESP Level 1 Foundational: BCD-06
- SCF CORE ESP Level 2 Critical Infrastructure: BCD-06
- SCF CORE ESP Level 3 Advanced Threats: BCD-06
- SCF CORE Mergers, Acquisitions & Divestitures (MA&D): BCD-06
Framework Mappings
- AICPA Trust Services Criteria (2017; revised Points of Focus 2022):
CC7.5,CC7.5-POF4,CC7.5-POF5 - Control Objectives for Information and Related Technologies (COBIT) (2019):
DSS04.05 - Cloud Security Alliance (CSA) Cloud Controls Matrix (CCM) v4.1.0:
BCR-04,BCR-09 - Cyber Resilience Capability Maturity Model (CR - CMM) (2026):
CR7.2.13 - Government Risk and Authorization Management Program (GovRAMP):
CP-02 - Government Risk and Authorization Management Program (GovRAMP) - Low:
CP-02 - Government Risk and Authorization Management Program (GovRAMP) - Low+:
CP-02 - Government Risk and Authorization Management Program (GovRAMP) - Moderate:
CP-02 - Government Risk and Authorization Management Program (GovRAMP) - High:
CP-02 - ISO/IEC 22301:2019 - Security and resilience - Business continuity management systems - Requirements:
6.3,6.3(a),6.3(b),8.6,8.6(a),8.6(b),8.6(c),8.6(d),8.6(e),10.2 - NIST SP 800 - 53 R4 - Security and Privacy Controls for Federal Information Systems and Organizations:
CP-2 - NIST SP 800 - 53 R5 - Security and Privacy Controls for Information Systems and Organizations:
CP-02 - NIST SP 800 - 53 R5 - Security and Privacy Controls for Information Systems and Organizations - Privacy Baseline:
CP-02 - NIST SP 800 - 53 R5 - Security and Privacy Controls for Information Systems and Organizations - Low Baseline:
CP-02 - NIST SP 800-82 Rev. 3 — Guide to Operational Technology (OT) Security:
CP-02 - NIST SP 800-82 Rev. 3 — Low Ot Overlay:
CP-02 - NIST SP 800-82 Rev. 3 — Moderate Ot Overlay:
CP-02 - NIST SP 800-82 Rev. 3 — High Ot Overlay:
CP-02 - NIST SP 800 - 161 R1 UDP1 - Cybersecurity Supply Chain Risk Management Practices for Systems and Organizations:
CP-2 - NIST SP 800 - 161 R1 UDP1 - Cybersecurity Supply Chain Risk Management Practices for Systems and Organizations - C - SCRM Baseline:
CP-2 - NIST SP 800 - 161 R1 UDP1 - Cybersecurity Supply Chain Risk Management Practices for Systems and Organizations - Level 2 Baseline:
CP-2 - NIST SP 800 - 161 R1 UDP1 - Cybersecurity Supply Chain Risk Management Practices for Systems and Organizations - Level 3 Baseline:
CP-2 - NIST Cybersecurity Framework v2.0: ID.IM-04
- US - Department of Justice - Criminal Justice Information Services (CJIS) Security Policy v6.0:
CP-2 - US - Department of Energy (DOE) - Cybersecurity Capability Maturity Model version 2.1:
RESPONSE-4p - US - Federal Risk and Authorization Management Program (FedRAMP) R5 - Low Baseline:
CP-02 - US - Federal Risk and Authorization Management Program (FedRAMP) R5 - Moderate Baseline:
CP-02 - US - Federal Risk and Authorization Management Program (FedRAMP) R5 - High Baseline:
CP-02 - US - Federal Risk and Authorization Management Program (FedRAMP) R5 - Li - SAAS Baseline:
CP-02 - US - Internal Revenue Service (IRS) 1075 (2021):
CP-2 - US - Centers for Medicare & Medicaid Services MARS - E Document Suite, Version 2.0:
CP-2,CP-2.e - US - North American Electric Reliability Corporation (NERC) Critical Infrastructure Protection (CIP) (2024):
CIP-009-6 3.1.3,CIP-009-6 3.2.1 - US - Texas DIR Security Control Standards Catalog v2.2:
CP-02 - US - Texas Risk & Authorization Management Program 2.0 - Level 1:
CP-02 - US - Texas Risk & Authorization Management Program 2.0 - Level 2:
CP-02 - EU - European Banking Authority Guidelines on ICT and Security Risk Management (2025):
3.7.4.88,3.7.4.90 - Germany - Cloud Computing Compliance Controls Catalogue (C5) (2020):
BCM-04 - Australia - Prudential Standard CPS 230 - Operational Risk Management (2023):
45
Minimum Security Requirements
- No MCR or DSR designation is specified in the source workbook.
Risk and Threat Mappings
Risks
-
R-AM-3 -
R-BC-1 -
R-BC-3 -
R-EX-1 -
R-EX-2 -
R-EX-3 -
R-EX-4 -
R-EX-5 -
R-EX-6 -
R-EX-7 -
R-GV-1 -
R-GV-2 -
R-GV-4 -
R-GV-5 -
R-IR-1 -
R-IR-2 -
R-IR-3 -
R-IR-4 -
R-SA-1
Threats
-
NT-7 -
MT-1 -
MT-2 -
MT-7 -
MT-8 -
MT-9 -
MT-10 -
MT-11 -
MT-12 -
MT-13 -
MT-14 -
MT-15 -
MT-24 -
MT-25 -
MT-27 -
MT-28
Source References
- Secure Controls Framework 2026.2 workbook
- SCF Overview & Practitioner Guidebook, version 2026.2