NERC CIP — CIP-003-11 R3 CIP Senior Manager
source: false
type: "canonical-control-reference"
standard: "NERC Critical Infrastructure Protection"
document_version: "CIP-003-11"
criterion_id: "CIP-003-11 R3"
family_id: "CIP-003-11"
family: "Cyber Security – Security Management Controls"
title: "CIP Senior Manager"
status: "approved-future-enforcement"
assessment_criterion: true
normative_text_included: true
updated: "2026-09-13"
source_pdf: "Resources/CMMC Brain 2.1/Sources/NERC CIP/CIP-003-11.pdf"
source_pages: [5, 12]
requirement_pages: [5]
us_effective_date: "07/01/2029"
mapping_status: "not-transferred-from-2024-SCF-set"
CIP-003-11 R3 CIP Senior Manager
Version and enforcement
U.S. status checked 2026-09-13: Subject to Future Enforcement. Standard effective date: 07/01/2029. Jurisdiction-specific applicability and transitional obligations must be checked against the implementation plan.
Requirement
Each Responsible Entity shall identify a CIP Senior Manager by name and document any change within 30 calendar days of the change. [Violation Risk Factor: Medium] [Time Horizon: Operations Planning]
Assessment Measure
An example of evidence may include, but is not limited to, a dated and approved document from a high-level official designating the name of the individual identified as the CIP Senior Manager.
Violation Severity Levels
Lower
The Responsible Entity did not document changes to the CIP Senior Manager within 30 calendar days but did document this change in less than 40 calendar days of the change. (Requirement R3)
Moderate
The Responsible Entity did not document changes to the CIP Senior Manager within 40 calendar days but did document this change in less than 50 calendar days of the change. (Requirement R3)
High
The Responsible Entity did not document changes to the CIP Senior Manager within 50 calendar days but did document this change in less than 60 calendar days of the change. (Requirement R3)
Severe
The Responsible Entity did not identify, by name, a CIP Senior Manager. OR The Responsible Entity did not document changes to the CIP Senior Manager within 60 calendar days of the change. (Requirement R3)
Applicability and Evidence Retention
CIP-003-11 applicability, exemptions, compliance monitoring, and evidence retention. Integral attachment(s): CIP-003-11 R2 attachments.
Referenced Publications
- CIP-003-11 official standard; PDF page(s) 5, 12. NERC original PDF.
- NERC standard status and dates (checked 2026-09-13).
- CIP-003-11 implementation plan. NERC original implementation plan.
Notes
- Assessment reference scope: the complete numbered requirement, associated parts and measures are kept together. Source wording is transcribed; line wrapping and presentation are normalized. The official PDF controls if a discrepancy is found.
- Table columns are presented as labeled subsections for each part so applicability, requirements, and measures remain associated.
- Publicly available does not mean public domain. This is an internal reference, not an NERC publication or endorsement.
- Legacy SCF relationships refer to the 2024 versioned mapping set; no cross-version equivalence is asserted.