CMMC 2.0 — CM.L3-03.04.07E Testing, Validation, and Documentation of Changes


source: false

type: canonical-control-reference

standard: CMMC 2.0

profile: "Level 3 additive SP 800-172r3 project baseline"

regulatory_status: "project-defined; not the current CMMC v2.13 Level 3 control selection"

document_version: "SP 800-172r3 project baseline"

level: 3

practice_id: "CM.L3-03.04.07E"

source_requirement_id: "03.04.07E"

family_id: "03.04"

domain_id: "CM"

family: "Configuration Management"

title: "Testing, Validation, and Documentation of Changes"

status: active

baseline_mode: additive

level_2_prerequisite: true

level_2_controls_duplicated: false

scoring_method: "one-point-per-additional-requirement project assumption"

point_value: 1

assessment_reevaluation: conditional

assessment_poam_eligible: "not-defined-for-project-baseline"

deferred_documentation: "re-evaluation-only"

updated: 2026-09-10

authoritative_sources:

- "NIST SP 800-172r3 verified transcription"

- "NIST SP 800-172Ar3 verified transcription"

- "32 CFR Part 170 CMMC Program Final Rule"

canonical_source_card: "NIST SP 800-172r3 03.04.07E"

source_controls:

- "NIST SP 800-53r5 CM-03(02)"

source_assessment_procedures:

- "NIST SP 800-53Ar5 CM-03(02)"


CM.L3-03.04.07E Testing, Validation, and Documentation of Changes

Project-defined additive Level 3 profile

This card applies the active NIST SP 800-172r3 enhanced requirement as an additional Level 3 requirement. It is not a representation of the current CMMC v2.13 selection of 24 NIST SP 800-172 (2021) requirements.

CMMC Level 3 — Additive Profile

Source for the scoring and re-evaluation model: 32 CFR Part 170, §§ 170.18(c)(2), 170.21, and 170.24(c)(3). Application to the complete SP 800-172r3 catalog is a project assumption.

NIST SP 800-172r3 — Enhanced Security Requirement

Test, validate, and document changes to the system before finalizing the implementation of the changes.

Discussion

Changes to systems include modifications to hardware, software, or firmware components and defined configuration settings. Organizations ensure that testing does not interfere with system operations that support organizational missions and business functions. Individuals or groups that conduct the tests understand the system security policies and procedures associated with the specific facilities or processes. Operational systems may need to be taken offline or replicated to the extent feasible before testing can be conducted. If systems must be taken offline for testing, the tests are scheduled to occur during planned system outages whenever possible. If the testing cannot be conducted on operational systems, organizations employ compensating protection measures. This requirement enhances SP 800-171 requirement 03.04.03.

Protection Strategy

PRA

Adversary Effects

Preclude (Preempt), Impede (Exert)

References

Source Controls — NIST SP 800-53r5

NIST SP 800-172Ar3 — Assessment Procedure

Assessment Objective

Determine if:

A.03.04.07E[01]: changes to the system are tested before finalizing the implementation of the changes. A.03.04.07E[02]: changes to the system are validated before finalizing the implementation of the changes.

A.03.04.07E[03]: changes to the system are documented before finalizing the implementation of the changes.

Assessment Methods and Objects

Examine

[SELECT FROM: Configuration management policy; configuration management plan; procedures addressing system configuration change control; system architecture and configuration documentation; system design documentation; test records; system configuration settings and associated documentation; validation records; change control records; system audit records; system security plan; other relevant documents or records].

Interview

[SELECT FROM: Personnel with configuration change control responsibilities; personnel with information security responsibilities; members of change control board or similar; system/network administrators; system developers].

Test

[SELECT FROM: Processes for configuration change control; mechanisms supporting and/or implementing, testing, validating, and documenting system changes].

References

Source Assessment Procedures — NIST SP 800-53Ar5