CMMC 2.0 — CM.L3-03.04.06E Retention of Previous Configurations
source: false
type: canonical-control-reference
standard: CMMC 2.0
profile: "Level 3 additive SP 800-172r3 project baseline"
regulatory_status: "project-defined; not the current CMMC v2.13 Level 3 control selection"
document_version: "SP 800-172r3 project baseline"
level: 3
practice_id: "CM.L3-03.04.06E"
source_requirement_id: "03.04.06E"
family_id: "03.04"
domain_id: "CM"
family: "Configuration Management"
title: "Retention of Previous Configurations"
status: active
baseline_mode: additive
level_2_prerequisite: true
level_2_controls_duplicated: false
scoring_method: "one-point-per-additional-requirement project assumption"
point_value: 1
assessment_reevaluation: conditional
assessment_poam_eligible: "not-defined-for-project-baseline"
deferred_documentation: "re-evaluation-only"
updated: 2026-09-10
authoritative_sources:
- "NIST SP 800-172r3 verified transcription"
- "NIST SP 800-172Ar3 verified transcription"
- "32 CFR Part 170 CMMC Program Final Rule"
canonical_source_card: "NIST SP 800-172r3 03.04.06E"
source_controls:
- "NIST SP 800-53r5 CM-02(03)"
source_assessment_procedures:
- "NIST SP 800-53Ar5 CM-02(03)"
CM.L3-03.04.06E Retention of Previous Configurations
Project-defined additive Level 3 profile
This card applies the active NIST SP 800-172r3 enhanced requirement as an additional Level 3 requirement. It is not a representation of the current CMMC v2.13 selection of 24 NIST SP 800-172 (2021) requirements.
CMMC Level 3 — Additive Profile
- Level 2 prerequisite: All Level 2 requirements remain prerequisites and are maintained only in CMMC 2.0 Level 2. They are not duplicated in this folder.
- Additional requirement source: NIST SP 800-172r3 03.04.06E.
- Point value: 1 point under this project profile, following the current CMMC Level 3 one-point-per-additional-requirement model.
- In-assessment correction / re-evaluation: Conditionally permitted for a NOT MET Level 3 requirement during the assessment and for 10 business days following the active assessment period, when additional evidence demonstrates MET, does not materially affect previously assessed requirements, and is provided before the Assessment Findings Report is delivered.
- Assessment POA&M: Not assigned at the individual-card level. The current regulatory exclusion list applies to the legacy 24-requirement CMMC v2.13 selection and cannot be accurately projected onto the complete SP 800-172r3 catalog without an approved successor mapping.
- Deferred documentation: No separate deferred-documentation finding is assumed. Draft, unofficial, or unapproved documentation is not acceptable evidence; corrections are handled through re-evaluation.
Source for the scoring and re-evaluation model: 32 CFR Part 170, §§ 170.18(c)(2), 170.21, and 170.24(c)(3). Application to the complete SP 800-172r3 catalog is a project assumption.
NIST SP 800-172r3 — Enhanced Security Requirement
Retain [Assignment: organization-defined number] previous versions of baseline configurations of the system to support rollback.
Discussion
Retaining previous versions of baseline configurations to support rollback includes configuration files for hardware, software, and firmware, configuration records, and associated documentation. This requirement enhances SP 800-171 requirement 03.04.01.
Protection Strategy
DLO, CRS
Adversary Effects
Preclude (Preempt), Impede (Exert), Limit (Shorten, Reduce)
References
Source Controls — NIST SP 800-53r5
NIST SP 800-172Ar3 — Assessment Procedure
Assessment Objective
Determine if:
A.03.04.06E.ODP[01]: the number of previous baseline configuration versions to be retained is defined.
A.03.04.06E: <A.03.04.06E.ODP[01]: number> previous versions of baseline configurations of the system are retained to support rollback.
Assessment Methods and Objects
Examine
[SELECT FROM: Configuration management policy; procedures addressing the baseline configuration of the system; configuration management plan; system architecture and configuration documentation; system configuration settings and associated documentation; copies of previous baseline configuration versions; system security plan; other relevant documents or records].
Interview
[SELECT FROM: Personnel with configuration management responsibilities; personnel with information security responsibilities; system/network administrators].
Test
[SELECT FROM: Processes for managing baseline configurations].