CMMC 2.0 — CM.L2-3.4.4 Security Impact Analysis
source: false
type: canonical-control-reference
standard: CMMC 2.0
document_version: "2.13"
level: 2
practice_id: "CM.L2-3.4.4"
family_id: "CM"
family: "Configuration Management"
title: "Security Impact Analysis"
status: active
scoring_method: weighted-deduction
point_value: 1
assessment_reevaluation: conditional
assessment_poam_eligible: true
deferred_documentation: "re-evaluation-only"
updated: 2026-09-10
authoritative_sources:
- "CMMC Level 2 Assessment Guide v2.13 transcription"
- "CMMC Level 2 Assessment Guide v2.13 PDF"
- "CMMC Assessment Process (CAP), Version 2.0"
- "32 CFR Part 170 CMMC Program Final Rule"
CM.L2-3.4.4 Security Impact Analysis
Canonical CMMC 2.0 reference
Complete practice guidance comes from the official CMMC Level 2 Assessment Guide, Version 2.13.
CMMC 2.0 — Practice
Analyze the security impact of changes prior to implementation.
Assessment Scoring and Correction
- Point value: 1-point deduction when the requirement is NOT MET.
- In-assessment correction / re-evaluation: Conditionally permitted for a NOT MET requirement during the assessment and for 10 business days following the active assessment period. Additional evidence must demonstrate MET, must not change or limit another requirement already scored MET, and must be submitted before delivery of the Assessment Findings Report.
- Assessment POA&M: Conditionally eligible if the assessment score is at least 80 percent and all other § 170.21 conditions are satisfied; closeout is required within 180 days.
- Deferred documentation: The current CAP does not define a separate deferred-documentation finding. Draft, unofficial, or unapproved documentation is unacceptable evidence; a corrected deficiency is handled through the re-evaluation procedure above.
Sources: CAP v2.0, § 2.15; 32 CFR Part 170, §§ 170.17(c)(2), 170.21, and 170.24.
Assessment Objectives — NIST SP 800-171A1
Determine if:
-
[a]— the security impact of changes to the system is analyzed prior to implementation.
Potential Assessment Methods and Objects — NIST SP 800-171A1
Examine
Select from:
- Configuration management policy
- procedures addressing security impact analysis for system changes
- configuration management plan
- security impact analysis documentation
- system security plan
- analysis tools and associated outputs
- change control records
- system audit logs and records
- other relevant documents or records
Interview
Select from:
- Personnel with responsibility for conducting security impact analysis
- personnel with information security responsibilities
- system or network administrators
Test
Select from:
- Organizational processes for security impact analysis
Discussion — NIST SP 800-171r22
Organizational personnel with information security responsibilities (e.g., system administrators, system security officers, system security managers, and systems security engineers) conduct security impact analyses. Individuals conducting security impact analyses possess the necessary skills and technical expertise to analyze the changes to systems and the associated security ramifications. Security impact analysis may include reviewing security plans to understand security requirements and reviewing system design documentation to understand the implementation of controls and how specific changes might affect the controls. Security impact analyses may also include risk assessments to better understand the impact of the changes and to determine if additional controls are required. NIST SP 800-128 provides guidance on configuration change control and security impact analysis.
Further Discussion
Changes to complex environments are reviewed for potential security impact before implemented. Changes to IT systems can cause unforeseen problems and have unintended consequences for both users and the security of the operating environment. Analyze the security impact of changes prior to implementing them. This can uncover and mitigate potential problems before they occur.
Example
You have been asked to deploy a new web browser plug-in. Your standard change management process requires that you produce a detailed plan for the change, including a review of its potential security impact. A subject-matter expert who did not submit the change reviews the plan and tests the new plug-in for functionality and security. You update the change plan based on the expert’s findings and submit it to the change control board for final approval [a].
Potential Assessment Considerations
- Are configuration changes tested, validated, and documented before installing them on the operational system
[a]?
Key References
Source References
- CMMC Level 2 Assessment Guide, Version 2.13
- CMMC Level 2 Scoping Guide, Version 2.13
- CMMC Model Overview, Version 2.13
Referenced Publications
1 NIST SP 800-171A, Assessing Security Requirements for Controlled Unclassified Information.
2 NIST SP 800-171 Revision 2, Protecting Controlled Unclassified Information in Nonfederal Systems and Organizations.