NERC CIP — CIP-009-7.1 R1 Recovery Plan Specifications
source: false
type: "canonical-control-reference"
standard: "NERC Critical Infrastructure Protection"
document_version: "CIP-009-7.1"
criterion_id: "CIP-009-7.1 R1"
family_id: "CIP-009-7.1"
family: "Cyber Security — Recovery Plans for BES Cyber Systems"
title: "Recovery Plan Specifications"
status: "approved-future-enforcement"
assessment_criterion: true
normative_text_included: true
updated: "2026-09-13"
source_pdf: "Resources/CMMC Brain 2.1/Sources/NERC CIP/CIP-009-7.1.pdf"
source_pages: [4, 5, 11]
requirement_pages: [4, 5]
us_effective_date: "07/01/2028"
mapping_status: "not-transferred-from-2024-SCF-set"
CIP-009-7.1 R1 Recovery Plan Specifications
Version and enforcement
U.S. status checked 2026-09-13: Subject to Future Enforcement. Standard effective date: 07/01/2028. Jurisdiction-specific applicability and transitional obligations must be checked against the implementation plan.
Requirement
Each Responsible Entity shall have one or more documented recovery plan(s) that collectively include each of the applicable Requirement Parts in CIP-009-7.1 Table R1 – Recovery Plan Specifications. [Violation Risk Factor: Medium] [Time Horizon: Long Term Planning].
Assessment Measure
Evidence must include the documented recovery plan(s) that collectively include the applicable Requirement Parts in CIP-009-7.1 Table R1 – Recovery Plan Specifications.
Requirement Parts
Part 1.1
Applicable Systems
High impact BCS and their associated:
-
1.Electronic Access Control or Monitoring Systems (EACMS); and
-
2.Physical Access Control Systems (PACS)
Medium impact BCS and their associated:
-
1.EACMS; and
-
2.PACS
Requirement
Conditions for activation of the recovery plan(s).
Measures
An example of evidence may include, but is not limited to, one or more plans that include language identifying conditions for activation of the recovery plan(s).
Part 1.2
Applicable Systems
High impact BCS and their associated:
-
1.EACMS; and
-
2.PACS
Medium impact BCS and their associated:
-
1.EACMS; and
-
2.PACS
Requirement
Roles and responsibilities of responders.
Measures
Examples of evidence may include, but are not limited to, one or more recovery plans that include language identifying the roles and responsibilities of responders.
Part 1.3
Applicable Systems
High impact BCS and their associated:
-
1.EACMS; and
-
2.PACS
Medium impact BCS and their associated:
-
1.EACMS; and
-
2.PACS
Requirement
One or more processes for the backup and storage of information required to recover Applicable System functionality.
Measures
An example of evidence may include, but is not limited to, documentation of specific processes for the backup and storage of information required to recover Applicable System functionality.
Part 1.4
Applicable Systems
High impact BCS and their associated:
-
1.EACMS; and
-
2.PACS
Medium impact BCS at Control Centers and their associated:
-
1.EACMS; and PACS
Requirement
One or more processes to verify the successful completion of the backup processes in Part 1.3 and to address any backup failures.
Measures
Examples of evidence may include, but are not limited to, logs, workflow or other documentation confirming that the backup process completed successfully and backup failures, if any, were addressed.
Part 1.5
Applicable Systems
High impact BCS and their associated:
-
1.EACMS; and
-
2.PACS
Medium impact BCS and their associated:
-
1.EACMS; and
-
2.PACS
SCI supporting an Applicable System in this part
Requirement
One or more processes to preserve data, per system capability, for determining the cause of a Cyber Security Incident that triggers activation of the recovery plan(s). Data preservation should not impede or restrict recovery.
Measures
Examples of evidence may include, but are not limited to, procedures to preserve data, such as preserving a corrupted drive or making a data mirror of the system before proceeding with recovery.
Violation Severity Levels
Lower
N/A
Moderate
The Responsible Entity’s plan(s) did not address one of the requirements included in Parts 1.2 through 1.5.
High
The Responsible Entity plan(s) did not address two of the requirements included in Parts 1.2 through 1.5.
Severe
The Responsible Entity did not create recovery plan(s) for Applicable Systems.
OR
The Responsible Entity plan(s) did not address the conditions for activation in Part 1.1.
OR
The Responsible Entity plan(s) did not address three or more of the requirements in Parts 1.2 through 1.5.
Applicability and Evidence Retention
CIP-009-7.1 applicability, exemptions, compliance monitoring, and evidence retention.
Referenced Publications
- CIP-009-7.1 official standard; PDF page(s) 4, 5, 11. NERC original PDF.
- NERC standard status and dates (checked 2026-09-13).
- CIP-009-7.1 implementation plan. NERC original implementation plan.
Notes
- Assessment reference scope: the complete numbered requirement, associated parts and measures are kept together. Source wording is transcribed; line wrapping and presentation are normalized. The official PDF controls if a discrepancy is found.
- Table columns are presented as labeled subsections for each part so applicability, requirements, and measures remain associated.
- Publicly available does not mean public domain. This is an internal reference, not an NERC publication or endorsement.
- Legacy SCF relationships refer to the 2024 versioned mapping set; no cross-version equivalence is asserted.