Refinement ConDa
Improvements for Refinement and Planning
Action item team retro 04 Jun 2024 → inspect and adapt after some weeks e.g. 25 Jun 2024
muss ich moderieren! Wie sorge ich für Schwung, speed, Detailbesprechung? Wo muss ich bei Jira clicken?
Refinement + Check in Planning
- In general: Go more into detail in the refinement.
- In general: Don't create monster stories with numerous subtasks.
- Look at the content of a story:
- Does it add value on its own? = story
- If not = subtask
- Make external dependencies visible --> because they entail higher risks.
- Make need for clarification with stakeholders visible:
- What needs to be aligned
- Who is responsible to do that?
- Try to make stories smaller/split, but not just for the sake of cutting smaller! They should still create value to our users
Planning
- Be strict: Take nothing which needs to be clarified into the sprint
- Clarification as an own task.
ConDa Refinement and Story Point Estimation Guide
Preparation for the Refinement Session
- Structure and Efficiency:
- Clear agenda
- Timebox each section (e.g., Story discussion 5-10 min, Estimation 3 min per story)
- Set expectations for participation
- Stories Readiness:
- Move stories to "Ready for Refinement"
- Ask the team to read stories in advance
- Focus Areas:
- Concrete discussion of each story
- Identify and document necessary implementation steps (Sub-Tasks)
- Conduct story point estimation
- Roles:
- You: Moderator, guide estimation, ensure structured flow
- Marike: Content owner, focus on discussion
Refinement
KeyBenefits of Refinement & Estimation
Refinement Benefits
- Clarity & Alignment– Ensures shared understanding before development.
- Better Planning– Identifies risks, dependencies, and necessary clarifications.
- Work Breakdown– Splits large stories into manageable, value-driven pieces.
- Higher Efficiency– Reduces rework by defining clear requirements early.
Estimation Benefits
- Realistic Sprint/Iteration Planning– Aligns workload with team capacity.
- Better Forecasting– Improves predictability and velocity tracking.
- Risk Mitigation– Highlights complex or unclear stories early.
- Team Collaboration– Encourages discussion and shared responsibility.
Objective Refinement
- Purpose: Discuss and estimate stories for the upcoming sprint/iteration
- Goal: Achieve clarity and consensus on Story Points.
Steps
- Discuss story details.
- Define necessary subtasks.
- Estimate Story Points using the agreed scale.
EstimationScale
- 1: Trivial
- 3: Manageable
- 5: Medium complexity
- 8: Complex, challenging
Participation Expectations
- Read stories in advance.
- Share your perspective in discussions.
- Support consensus in estimations