BAYAN KHUNDI GOLD PROJECT

The Bayan Khundii gold deposit is located in southwestern Mongolia, within the Khundii Gold District, approximately 16 kilometres south of the Altan Nar deposit. In August of 2019, Erdene secured a mining license for Bayan Khundii from the Mineral Resource and Petroleum Authority of Mongolia (“MRPAM”). The Bayan Khundii mining license covers 2,309 hectares and, in addition to the Bayan Khundii high-grade gold deposit, includes Erdene’s highly prospective Altan Arrow, Dark Horse (Khar Mori) and Khundii North prospects. The mining license is valid for an initial term of 30 years with the ability to extend to 70 years.

Bankable Feasibility Study

In July 2020, Erdene announced the results of an independent Bankable Feasibility Study (“BFS”) for Bayan Khundii Gold Project. The BFS included an updated Mineral Reserve for Bayan Khundii. Please refer to the Company’s July 20, 2020 news release and the BFS NI 43-101 Technical Reportfor full details.

BFS highlights (assuming US $1,400/oz gold price):

Mineral Resources and Reserves

Bayan Khundii Gold Deposit –Mineral Resource Estimate for Cut-off Grade of 0.55 g/t Gold (Au), October 1, 2019

Mineral Resource ClassificationQuantity (Mt)Grade (g/t Au)Contained Au (Koz)
Measured1.43.77171
Indicated3.72.93350
Measured & Indicated5.13.16521
Inferred0.93.68103

Bayan Khundii Gold Deposit – Mineral Reserve Statement, July 1, 2020

Mineral Reserve ClassificationQuantity (Mt)Grade (g/t Au)Contained Au (Koz)
Proven1.24.2166
Probable2.23.5244
Total Mineral Reserve3.43.7409

Please refer to the Company’s July 20, 2020 news releaseand the BFS NI 43-101 Technical Report for full details.

Project Financing

In November 2020, Erdene announced (press release) that it executed a mandate letter with Export Development Canada (“EDC”) for an up to US$55 million senior secured debt facility to develop the Bayan Khundii Gold Project. EDC’s financing for the Project is conditional upon the satisfactory completion of due diligence.

Construction Readiness

Work to advance the Bayan Khundii Gold Project towards construction and development are ongoing. Construction readiness activities have commenced, including:

Environmental, Social, and Governance

Erdene continues ongoing stakeholder engagement activities for the ESIA and the Mongolian statutory Detailed Environmental Impact Assessment (“DEIA”), including:

To date, Erdene has obtained key permits and advanced regulatory approvals required for mine development, including:

Upside Potential

In August 2020, Erdene commenced a planned 18,000-metre drill program at its Khundii Gold District. At year-end 2020, 14,300 metres were completed, consisted of 9,345 metres over 54 holes (including four extension holes) at Bayan Khundii and 4,660 metres over 25 holes at the recently discovered Dark Horse prospect located on the Bayan Khundii Mining license. Results at the Midfield North and Striker SW Bayan Khundii zones included several high-grade intersections outside the Bayan Khundii economic pit that have the potential to add to Bayan Khundii resources meaningfully.

Drilling at Dark Horse included the discovery of a new high-grade, shallow, gold discovery, including multiple holes reporting wide zones of mineralization (from 45 m of 5.97 g/t Au to 130 metres of 0.54 g/t Au) with higher-grade intersections up to 22 metres of 21.2 g/t Au. These drill holes are hosted in a 4-kilometre long structure in the western portion of the Dark Horse target area, demonstrating the potential for significant gold discoveries near the Bayan Khundii deposit. Please refer to the Dark Horse Project pagefor further details.

In addition to Dark Horse, there are several other prospects located on the Khundii Mining license with significant upside potential, including:

The Bayan Khundii license has a 1.0% net smelter returns royalty (“NSR Royalty”) in favour of Sandstorm Gold Ltd.

Peter Dalton, P.Geo. (Nova Scotia), Senior Geologist, Erdene Resource Development Corporation, is a Qualified Person within the meaning of National Instrument 43-101 and has reviewed and approved the scientific and technical information contained herein.