Open in TheBrain

BEACON HILL

Fully permitted and 750 tpd capacity

The Beacon Mill has a 750 tpd capacity. The mill is located on a property that consists of a mining lease, a mining concession, and 11 mining claims covering an area of 1.8 km2. The property also has tailings management ponds, underground installations, a 500-metre deep shaft and a mechanical shop. The plant is located in Val-d’Or on highway 117 at less than 10km from the Beaufor Mine and at proximity to the railway system.

The Beacon Mill is fully permitted, including a certificate of authorization by the ministère du Développement durable, de l’Environnement et de la Lutte contre les changements climatiques for the processing of 1,800,000 tonnes of tailings, equivalent to approximately nine years of mineral processing at full capacity.