NERC CIP — CIP-014-4 R7 Control Center Notification
source: false
type: "canonical-control-reference"
standard: "NERC Critical Infrastructure Protection"
document_version: "CIP-014-4"
criterion_id: "CIP-014-4 R7"
family_id: "CIP-014-4"
family: "Physical Security"
title: "Control Center Notification"
status: "approved-future-enforcement"
assessment_criterion: true
normative_text_included: true
updated: "2026-09-13"
source_pdf: "Resources/CMMC Brain 2.1/Sources/NERC CIP/CIP-014-4.pdf"
source_pages: [5, 14, 15]
requirement_pages: [5]
us_effective_date: "10/01/2028"
mapping_status: "not-transferred-from-2024-SCF-set"
CIP-014-4 R7 Control Center Notification
Version and enforcement
U.S. status checked 2026-09-13: Subject to Future Enforcement. Standard effective date: 10/01/2028. Jurisdiction-specific applicability and transitional obligations must be checked against the implementation plan.
Requirement
For a primary control center(s) identified by the Transmission Owner according to Requirement R5, Part 5.3 that a) operationally controls an identified Transmission station or Transmission substation verified according to Requirement R6, and b) is not under the operational control of the Transmission Owner: the Transmission Owner shall, within seven calendar days following completion of Requirement R6, notify the Transmission Operator that has operational control of the primary control center of such identification and the date of completion of Requirement R6. [Violation Risk Factor: Lower; Time-Horizon: Long-term Planning]
-
7.1.If a Transmission station or Transmission substation previously identified under Requirements R1 and R5 and verified according to Requirement R6 is removed from the identification during a subsequent risk assessment performed according to Requirement R5 or a verification according to Requirement R6, then the Transmission Owner shall, within seven calendar days following the verification or the subsequent risk assessment, notify the Transmission Operator that has operational control of the primary control center of the removal.
Assessment Measure
Examples of acceptable evidence may include, but are not limited to, written or electronic notifications or communications that the Transmission Owner notified each Transmission Operator, as applicable, according to Requirement R7.
Violation Severity Levels
Lower
The Transmission Owner notified the Transmission Operator that operates the primary control center as specified in Requirement R7, but did so more than seven calendar days and less than or equal to nine calendar days following the completion of Requirement R6. OR The Transmission Owner notified the Transmission Operator that operates the primary control center of the removal from the identification in Requirement R5, but did so more than seven calendar days and less than or equal to nine calendar days following the verification or the subsequent risk assessment.
Moderate
The Transmission Owner notified the Transmission Operator that operates the primary control center as specified in Requirement R7, but did so more than nine calendar days and less than or equal to 11 calendar days following the completion of Requirement R6. OR The Transmission Owner notified the Transmission Operator that operates the primary control center of the removal from the identification in Requirement R5, but did so more than nine calendar days and less than or equal to 11 calendar days following the verification or the subsequent risk assessment.
High
The Transmission Owner notified the Transmission Operator that operates the primary control center as specified in Requirement R7, but did so more than 11 calendar days and less than or equal to 13 calendar days following the completion of Requirement R6. OR The Transmission Owner notified the Transmission Operator that operates the primary control center of the removal from the identification in Requirement R5, but did so more than 11 calendar days and less than or equal to 13 calendar days following the verification or the subsequent risk assessment.
Severe
The Transmission Owner notified the Transmission Operator that operates the primary control center as specified in Requirement R7, but did so more than 13 calendar days following the completion of Requirement R6. OR The Transmission Owner failed to notify the Transmission Operator that it operates a control center identified in Requirement R5. OR The Transmission Owner notified the Transmission Operator that operates the primary control center of the removal from the identification in Requirement R5, but did so more than 13 calendar days following the verification or the subsequent risk assessment. OR The Transmission Owner failed to notify the Transmission Operator that operates the primary control center of the removal from the identification in Requirement R5.
Applicability and Evidence Retention
CIP-014-4 applicability, exemptions, compliance monitoring, and evidence retention. Integral attachment(s): CIP-014-4 R1 attachments.
Referenced Publications
- CIP-014-4 official standard; PDF page(s) 5, 14, 15. NERC original PDF.
- NERC standard status and dates (checked 2026-09-13).
- CIP-014-4 implementation plan. NERC original implementation plan.
Notes
- Assessment reference scope: the complete numbered requirement, associated parts and measures are kept together. Source wording is transcribed; line wrapping and presentation are normalized. The official PDF controls if a discrepancy is found.
- Table columns are presented as labeled subsections for each part so applicability, requirements, and measures remain associated.
- Publicly available does not mean public domain. This is an internal reference, not an NERC publication or endorsement.
- Legacy SCF relationships refer to the 2024 versioned mapping set; no cross-version equivalence is asserted.