title: "Criteria for Instability"
status: "approved-future-enforcement"
assessment_criterion: true
normative_text_included: true
updated: "2026-09-13"
source_pdf: "Resources/CMMC Brain 2.1/Sources/NERC CIP/CIP-014-4.pdf"
source_pages: [3, 11, 12]
requirement_pages: [3]
us_effective_date: "10/01/2028"
mapping_status: "not-transferred-from-2024-SCF-set"
CIP-014-4 R4 Criteria for Instability
Version and enforcement
U.S. status checked 2026-09-13: Subject to Future Enforcement. Standard effective date: 10/01/2028. Jurisdiction-specific applicability and transitional obligations must be checked against the implementation plan.
Requirement
Each Transmission Owner with applicable Transmission station(s) and Transmission substation(s) identified in Requirement R1 jointly owned by multiple Transmission Owners shall coordinate with each appropriate Transmission Owner(s) to determine and document their individual and joint responsibilities under Requirement R3 and Requirement R5. [Violation Risk Factor: Medium; Time-Horizon: Operations Planning, Long-term Planning]
Assessment Measure
Examples of acceptable evidence may include, but are not limited to, dated documentation, such as meeting minutes, agreements, and email correspondence, that identifies that agreement has been reached on individual and joint responsibilities for performing the required risk assessments.
Violation Severity Levels
Lower
The Transmission Owner with applicable Transmission station(s) and Transmission substation(s) identified in Requirement R1 owned by multiple Transmission Owners failed to coordinate with each appropriate Transmission Owner(s) to determine and document their individual and joint responsibilities for documenting a risk assessment methodology under Requirement R3 and for performing any required risk assessments per Requirement R5 for less than or equal to 25% of jointly owned applicable Transmission station(s) and Transmission substation(s).
Moderate
The Transmission Owner with applicable Transmission station(s) and Transmission substation(s) identified in Requirement R1 owned by multiple Transmission Owners failed to coordinate with each appropriate Transmission Owner(s) to determine and document their individual and joint responsibilities for documenting a risk assessment methodology under Requirement R3 and for performing any required risk assessments per Requirement R5 for more than 25% and less than or equal to 50% of jointly owned applicable Transmission station(s) and Transmission substation(s).
High
The Transmission Owner with applicable Transmission station(s) and Transmission substation(s) identified in Requirement owned by multiple Transmission Owners failed to coordinate with each appropriate Transmission Owner(s) to determine and document their individual and joint responsibilities for documenting a risk assessment methodology under Requirement R3 and for performing any required risk assessments per Requirement R5 for more than 50% and less than or equal to 75% of jointly owned applicable Transmission station(s) and Transmission substation(s).
Severe
The Transmission Owner with applicable Transmission station(s) and Transmission substation(s) identified in Requirement R1 owned by multiple Transmission Owners failed to coordinate with each appropriate Transmission Owner(s) to determine and document their individual and joint responsibilities for documenting a risk assessment methodology under Requirement R3 and for performing any required risk assessments per Requirement R5 for more than 75% and less than or equal to 100% of any evidence for jointly owned applicable Transmission station(s) and Transmission substation(s).
Applicability and Evidence Retention
CIP-014-4 applicability, exemptions, compliance monitoring, and evidence retention. Integral attachment(s): CIP-014-4 R1 attachments.
Referenced Publications
- CIP-014-4 official standard; PDF page(s) 3, 11, 12. NERC original PDF.
- NERC standard status and dates (checked 2026-09-13).
- CIP-014-4 implementation plan. NERC original implementation plan.
Notes
- Assessment reference scope: the complete numbered requirement, associated parts and measures are kept together. Source wording is transcribed; line wrapping and presentation are normalized. The official PDF controls if a discrepancy is found.
- Table columns are presented as labeled subsections for each part so applicability, requirements, and measures remain associated.
- Publicly available does not mean public domain. This is an internal reference, not an NERC publication or endorsement.
- Legacy SCF relationships refer to the 2024 versioned mapping set; no cross-version equivalence is asserted.