NERC CIP — CIP-014-4 R5 Physical Security Risk Assessment


source: false

type: "canonical-control-reference"

standard: "NERC Critical Infrastructure Protection"

document_version: "CIP-014-4"

criterion_id: "CIP-014-4 R5"

family_id: "CIP-014-4"

family: "Physical Security"

title: "Physical Security Risk Assessment"

status: "approved-future-enforcement"

assessment_criterion: true

normative_text_included: true

updated: "2026-09-13"

source_pdf: "Resources/CMMC Brain 2.1/Sources/NERC CIP/CIP-014-4.pdf"

source_pages: [3, 4, 12, 13]

requirement_pages: [3, 4]

us_effective_date: "10/01/2028"

mapping_status: "not-transferred-from-2024-SCF-set"


CIP-014-4 R5 Physical Security Risk Assessment

Version and enforcement

U.S. status checked 2026-09-13: Subject to Future Enforcement. Standard effective date: 10/01/2028. Jurisdiction-specific applicability and transitional obligations must be checked against the implementation plan.

Requirement

At least once every 36 calendar months, each Transmission Owner shall perform a risk assessment to identify applicable Transmission station(s) and Transmission substation(s) identified in Requirement R1, that if rendered inoperable or damaged could result in instability, uncontrolled separation, or Cascading within an Interconnection, using the methodology established in Requirement R3. Jointly owned Transmission station(s) and Transmission substation(s) shall be assessed according to the responsibilities documented under Requirement R4. If proximate BES station(s) and BES Transmission substation(s) were identified in Requirement R2, they shall be included in the risk assessment according to Requirement R3, Part 3.3. [Violation Risk Factor: High; Time-Horizon: Operations Planning, Long-term Planning]

Assessment Measure

Examples of acceptable evidence may include, but are not limited to, dated written or electronic documentation of the risk assessment satisfying Requirement R5 including the identified Transmission station(s) or Transmission substation(s). For Requirement R5, Part 5.3, examples of acceptable evidence may include, but are not limited to, dated written or electronic documentation of the identification of the primary control center that operationally controls each identified Transmission station or Transmission substation.

Violation Severity Levels

Lower

The Transmission Owner performed a risk assessment, but did so after 36 calendar months, but less than or equal to 38 calendar months.

Moderate

The Transmission Owner performed a risk assessment, but did so after 38 calendar months, but less than or equal to 40 calendar months. OR The Transmission Owner performed a risk assessment inconsistent with one of the methodology requirements listed in Requirement R3, Parts 3.1 through 3.3.

High

The Transmission Owner performed a risk assessment, but did so after 40 calendar months, but less than or equal to 42 calendar months. OR The Transmission Owner performed a risk assessment inconsistent with two of the methodology requirements listed in Requirement R3, Parts 3.1 through 3.3. OR The Transmission Owner performed a risk assessment, but failed to include the primary control center identified in Part 5.2.

Severe

The Transmission Owner performed a risk assessment, but did so after more than 42 calendar months. OR The Transmission Owner performed a risk assessment inconsistent with all three of the methodology requirements listed in Requirement R3, Parts 3.1 through 3.3.

Applicability and Evidence Retention

CIP-014-4 applicability, exemptions, compliance monitoring, and evidence retention. Integral attachment(s): CIP-014-4 R1 attachments.