Open in TheBrain

NERC CIP — CIP-014-4 R8 Threat and Vulnerability Evaluation


source: false

type: "canonical-control-reference"

standard: "NERC Critical Infrastructure Protection"

document_version: "CIP-014-4"

criterion_id: "CIP-014-4 R8"

family_id: "CIP-014-4"

family: "Physical Security"

title: "Threat and Vulnerability Evaluation"

status: "approved-future-enforcement"

assessment_criterion: true

normative_text_included: true

updated: "2026-09-13"

source_pdf: "Resources/CMMC Brain 2.1/Sources/NERC CIP/CIP-014-4.pdf"

source_pages: [6, 15]

requirement_pages: [6]

us_effective_date: "10/01/2028"

mapping_status: "not-transferred-from-2024-SCF-set"


CIP-014-4 R8 Threat and Vulnerability Evaluation

Version and enforcement

U.S. status checked 2026-09-13: Subject to Future Enforcement. Standard effective date: 10/01/2028. Jurisdiction-specific applicability and transitional obligations must be checked against the implementation plan.

Requirement

Each Transmission Owner that identified a Transmission station, Transmission substation, or a primary control center in Requirement R5 and verified according to Requirement R6, and each Transmission Operator notified by a Transmission Owner according to Requirement R7, shall conduct an evaluation of the potential threats and vulnerabilities of a physical attack to each of their respective Transmission station(s), Transmission substation(s), and primary control center(s) identified in Requirement R5 and verified according to Requirement R6. The evaluation shall consider the following: [Violation Risk Factor: Medium; Time-Horizon: Operations Planning, Long- term Planning]

Assessment Measure

Examples of evidence may include, but are not limited to, dated written or electronic documentation that the Transmission Owner or Transmission Operator conducted an evaluation of the potential threats and vulnerabilities of a physical attack to their respective Transmission station(s), Transmission substation(s), and primary control center(s) as specified in Requirement R8.

Violation Severity Levels

Lower

N/A

Moderate

The responsible entity conducted an evaluation of the potential physical threats and vulnerabilities to each of its Transmission station(s), Transmission substation(s), and primary control center(s) identified in Requirement R5, but failed to consider one of Parts 8.1 through 8.3 in the evaluation.

High

The responsible entity conducted an evaluation of the potential physical threats and vulnerabilities to each of its Transmission station(s), Transmission substation(s), and primary control center(s) identified in Requirement R5, but failed to consider two of Parts 8.1 through 8.3 in the evaluation.

Severe

The responsible entity failed to conduct an evaluation of the potential physical threats and vulnerabilities to each of its Transmission station(s), Transmission substation(s), and primary control center(s) identified in Requirement R5. OR The responsible entity conducted an evaluation of the potential physical threats and vulnerabilities to each of its Transmission station(s), Transmission substation(s), and primary control center(s) identified in Requirement R5, but failed to consider Parts 8.1 through 8.3.

Applicability and Evidence Retention

CIP-014-4 applicability, exemptions, compliance monitoring, and evidence retention. Integral attachment(s): CIP-014-4 R1 attachments.

Referenced Publications

Notes