status: "approved-future-enforcement"

assessment_criterion: true

normative_text_included: true

updated: "2026-09-13"

source_pdf: "Resources/CMMC Brain 2.1/Sources/NERC CIP/CIP-014-4.pdf"

source_pages: [6, 7, 16, 17]

requirement_pages: [6, 7]

us_effective_date: "10/01/2028"

mapping_status: "not-transferred-from-2024-SCF-set"


CIP-014-4 R9 Physical Security Plans

Version and enforcement

U.S. status checked 2026-09-13: Subject to Future Enforcement. Standard effective date: 10/01/2028. Jurisdiction-specific applicability and transitional obligations must be checked against the implementation plan.

Requirement

Each Transmission Owner that identified a Transmission station, Transmission substation, or primary control center in Requirement R5 and verified according to Requirement R6, and each Transmission Operator notified by a Transmission Owner according to Requirement R7, shall develop and implement a documented physical security plan(s) that covers their respective Transmission station(s), Transmission substation(s), and primary control center(s). The physical security plan(s) shall be developed within 120 calendar days following the completion of Requirement R6 and executed according to the timeline specified in the physical security plan(s). The physical security plan(s) shall include the following attributes: [ Violation Risk Factor: High; Time-Horizon: Long-term Planning ]

Assessment Measure

Examples of evidence may include, but are not limited to, dated written or electronic documentation of its physical security plan(s) that covers their respective identified and verified Transmission station(s), Transmission substation(s), and primary control center(s) as specified in Requirement R6, and additional evidence demonstrating execution of the physical security plan according to the timeline specified in the physical security plan.

Violation Severity Levels

Lower

The responsible entity developed and implemented a documented physical security plan(s) that covers each of its Transmission station(s), Transmission substation(s), and primary control center(s) identified in Requirement R5, but did so more than 120 calendar days, but less than or equal to 130 calendar days after completing Requirement R6. OR The responsible entity developed and implemented a documented physical security plan(s) that covers its Transmission station(s), Transmission substation(s), and primary control center(s) identified in Requirement R5 and verified according to Requirement R6, but failed to include one of Parts 9.1 through 9.4 in the plan.

Moderate

The responsible entity developed and implemented a documented physical security plan(s) that covers each of its Transmission station(s), Transmission substation(s), and primary control center(s) identified in Requirement R5, but did so more than 130 calendar days, but less than or equal to 140 calendar days after completing Requirement R6. OR The responsible entity developed and implemented a documented physical security plan(s) that covers its Transmission station(s), Transmission substation(s), and primary control center(s) identified in Requirement R5 and verified according to Requirement R6, but failed to include two of Parts 9.1 through 9.4 in the plan.

High

The responsible entity developed and implemented a documented physical security plan(s) that covers each of its Transmission station(s), Transmission substation(s), and primary control center(s) identified in Requirement R5, but did so more than 140 calendar days, but less than or equal to 150 calendar days after completing Requirement R6. OR The responsible entity developed and implemented a documented physical security plan(s) that covers its Transmission station(s), Transmission substation(s), and primary control center(s) identified in Requirement R5 and verified according to Requirement R6, but failed to include three of Parts 9.1 through 9.4 in the plan.

Severe

The responsible entity developed and implemented a documented physical security plan(s) that covers each of its Transmission station(s), Transmission substation(s), and primary control center(s) identified in Requirement R5, but did so more than 150 calendar days after completing the verification in Requirement R6. OR The responsible entity failed to develop and implement a documented physical security plan(s) that covers its Transmission station(s), Transmission substation(s), and primary control center(s) identified in Requirement R5 and verified according to Requirement R6. OR The responsible entity developed and implemented a documented physical security plan(s) that covers its Transmission station(s), Transmission substation(s), and primary control center(s) identified in Requirement R5 and verified according to Requirement R6, but failed to include Parts 9.1 through 9.4 in the plan.

Applicability and Evidence Retention

CIP-014-4 applicability, exemptions, compliance monitoring, and evidence retention. Integral attachment(s): CIP-014-4 R1 attachments.

Referenced Publications

Notes